The Project for the New Uffizi
Organisation and prevention measures
The Uffizi site is comprised of six homogenous areas of intervention, each broken down into one or more work sites (operational lots). For each of these the following features have been identified: the logistic areas of support for the installation of the materials and the equipment, the boundaries, the routes connecting with the working areas (direct links or via scaffolding, elevators etc.), the entrance and exit routes etc. The individual work sites have been divided for functional and operational reasons into one or more environmental units
(U.A.).
Magliabechiana area
WORK SITE 1
Workshops and reception
Workshops and reception
Creation of the workshops and the reception area. Affects prevalently the lower floors of the Museum library.
WORK SITE 2
Security staff changing rooms
Security staff changing rooms
Creation of the changing-rooms and bathrooms for the security staff, located in the mezzanine above the museum exit.
South east area
WORK SITE 1
Veliti
Veliti
Installation of new lift in Palazzo dei Veliti. Creation of offices on the upper floors of the building.
WORK SITE 2
Archaeological and utility rooms
Archaeological and utility rooms
Creation of new utility rooms in the basement and an archaeological section in the old Medici stables.
WORK SITE 3
Tapestries and Auditorium
Tapestries and Auditorium
Creation on the ground floor of the tapestries section and an auditorium
WORK SITE 4
Gallery
Gallery
Rehabilitation of new display rooms on the first floor formerly occupied by the State Archive.
North west area
WORK SITE 1
West staircase and photographic archive
West staircase and photographic archive
Creation of the new staircase connecting the internal courtyard, and renovation of the ground floor rooms to be destined to the photographic archive
WORK SITE 2
Gallery and repositories
Gallery and repositories
Rehabilitation for display purposes of the rooms on the first floor previously destined to the State Archive.
Rehabilitation for display purposes of the rooms on the first floor previously destined to the State Archive.
Rehabilitation for display purposes of the rooms on the first floor previously destined to the State Archive.
South west area
WORK SITE 1
Utility rooms and display rooms
Utility rooms and display rooms
Creation of the new utility rooms on the mezzanine floor. Rehabilitation for display purposes of the rooms on the first floor, rear side.
WORK SITE 2
Gallery corridor
Gallery corridor
Rehabilitation for display purposes of the rooms of the first floor corridor
North east area
WORK SITE 1
Western staircase and display rooms
Western staircase and display rooms
Creation of new staircase connecting the ground and first floors. Rehabilitation for display purposes of the rooms on the mezzanine floor.
WORK SITE 2
Cloakroom, Educational facilities and Bookshop
Cloakroom, Educational facilities and Bookshop
Creation of the new cloakroom and the areas dedicated to educational activities in the basement. The new bookshop will be created on the ground floor
WORK SITE 3
Gallery
Gallery
Rehabilitation for display purposes of the rooms on the first floor corridor
WORK SITE 4
Botticelli and Primitives rooms
Botticelli and Primitives rooms
Reorganisation of the museum rooms
The Project 